Phase 2 Plan — CP-SAT Sequencing, Constraint Catalog, and LLM Agent Loop

Companion to PROBLEM_AND_APPROACH.md (overall architecture) and MODEL_SCOPING.md (decision variables / constraints). Where Phase 1 (/demo_scheduler/) is a single MILP that hardcodes the 15+3 constraints, Phase 2 turns the solver into a two-stage MILP + CP-SAT pipeline driven by a versioned constraint catalog, with seven LLM agents bridging the user, the catalog, and the solvers.


0. Why this phase

Phase 1 answered "can we even solve this?" — yes, the v1 MILP reaches 95% OTIF on Q1 in 10 min. Phase 2 answers three questions that block real adoption:

  1. Can we sequence tightly? v1 linearises sequence-dependent setup with big-M, so the changeover model is loose and slow. CP-SAT handles no_overlap, circuit, and forbidden regions natively — typically 5–10× faster on sequencing.
  2. Can the business edit a constraint without a code change? v1 puts the 15+3 constraints in Python and the parameters in YAML. Phase 2 moves every constraint (rule + parameters + scope) into a versioned catalog. Adding "Piramal band rises to 2.5M in Q3" is a one-row edit.
  3. Can an LLM safely propose / explain / re-plan changes? Phase 2 introduces 7 agents around the solvers. The LLM only ever writes catalog patches and narrations; numbers come from the solvers. A deterministic verifier sits between every agent output and the system of record.

1. End-state architecture (one diagram)

                           ┌────────────────────────┐
                           │      USER LAYER        │
                           │  chat • what-if forms  │
                           │  approval queue • KPI  │
                           └──────────┬─────────────┘
                                      │ NL request / structured patch
                                      ▼
        ┌─────────────────────────────────────────────────────────────┐
        │           AGENT ORCHESTRATION (LangGraph supervisor)        │
        │                                                             │
        │   ┌──────────────┐                                          │
        │   │ Supervisor   │  routes by intent                        │
        │   └──────┬───────┘                                          │
        │          │                                                  │
        │  ┌───────┴─────────────────────────────────────────────────┐│
        │  │ PRE-SOLVE                                               ││
        │  │   1) Constraint-Elicitation Agent (NL → catalog patch)  ││
        │  │   2) Schedule-Generation Agent (catalog → solver call)  ││
        │  └───────┬─────────────────────────────────────────────────┘│
        │          │                                                  │
        │          ▼                                                  │
        │     ╔══════════════════════════════════════════════╗        │
        │     ║         VERIFIER (deterministic)             ║        │
        │     ║  schema • unit • feasibility (warm cache)    ║        │
        │     ║  business-rule • audit-log                   ║        │
        │     ╚════════════════════╤═════════════════════════╝        │
        │                          │ (catalog committed)              │
        │                          ▼                                  │
        │  ┌──────────────────────────────────────────────────────┐   │
        │  │ SOLVER CHAIN (the source of truth on every number)   │   │
        │  │                                                      │   │
        │  │   Tier-1 LP        annual feasibility, O*            │   │
        │  │   Tier-2 MILP      assignment + customer bands       │◀──┤
        │  │   Tier-3 CP-SAT    sequencing + setup + no-overlap   │   │
        │  │   Tier-4 LNS       repair on live disruption         │   │
        │  │   DES Simulator    robustness validation             │   │
        │  └────────────────────┬─────────────────────────────────┘   │
        │                       │ solved plan + KPIs                  │
        │                       ▼                                     │
        │  ┌──────────────────────────────────────────────────────┐   │
        │  │ POST-SOLVE                                           │   │
        │  │   3) Infeasibility Agent  (OptiChat-style narration) │   │
        │  │   4) What-If Agent        (OptiGuide-style diffs)    │   │
        │  │   5) Explanation Agent    (persona-tuned rendering)  │   │
        │  └──────────────────────────────────────────────────────┘   │
        │                                                             │
        │  ┌──────────────────────────────────────────────────────┐   │
        │  │ LIVE (post-deploy)                                   │   │
        │  │   6) Disruption-Response Agent (ALAS-style LNS)      │   │
        │  └──────────────────────────────────────────────────────┘   │
        └─────────────────────────────────────────────────────────────┘
                                      │
                                      ▼
        ┌─────────────────────────────────────────────────────────────┐
        │  TOOL / DATA LAYER (every box is an MCP server)             │
        │  Catalog • Solver • SAP Bridge • Telemetry • Simulator      │
        │  Audit + version store                                      │
        └─────────────────────────────────────────────────────────────┘

2. CP-SAT sequencing — the second solver

2.1 Two-stage split

The MILP keeps everything where assignment + cumulative balance is naturally linear; CP-SAT takes everything where order matters within a (machine, week).

Concern v1 (Phase 1) v2 (Phase 2)
Order → (machine, week) assignment MILP MILP (Tier-2)
Demand fulfilment / unfilled MILP MILP (Tier-2)
Capacity hours per (m, w) MILP MILP (Tier-2)
Customer band (Piramal etc.) MILP soft slack MILP soft slack
Org no-split MILP MILP
Format-once-per-cycle MILP y_pack MILP y_pack
Production lag, cumulative MILP MILP
Sequence within a week (which order runs first) not modelled CP-SAT (Tier-3) — interval / no-overlap
Sequence-dependent setup duration big-M on consecutive-week y_pack CP-SAT transition_time / circuit
No-overlap of changeover team across machines linearised, weekly-coarse CP-SAT add_no_overlap on interval vars
Shift-level Gantt + start/finish times not modelled CP-SAT outputs minute-granularity intervals
EVATON 2-batch / 3-week gap structural placeholder CP-SAT forbidden_assignments

2.2 Data handoff between MILP and CP-SAT

Tier-2 MILP                        Tier-3 CP-SAT
───────────                        ────────────
solves over WEEKS                  solves over MINUTES (within each week)

writes:                            reads:
  x_pack[o,m,w]   ──────────────►    set of orders assigned to (m, w)
  y_pack[m,f,w]   ──────────────►    active format on (m, w)
  vol_pack[o,m,w] ──────────────►    quantity to pack
  qty_prod[s,w]   ──────────────►    production needs per week
                                   writes:
                                     interval_var(start, end) per order
                                     transition interval per changeover
                                     verified weekly Gantt
                                     refined changeover/idle hours
                                   feeds back (only on failure):
                                     "this week's MILP assignment is
                                      sequence-infeasible; retry"

The two solvers are not co-optimised in a Benders loop in v2 — the MILP commits its assignment and CP-SAT respects it. If CP-SAT can't sequence what MILP gave it (which is rare with sensible inputs), the failed week's x_pack and y_pack are sent back as a cut (forbidden combination) and MILP re-solves that week. Two iterations is normally enough.

2.3 What changes in the codebase

demo_scheduler/
├── model/
│   ├── build.py            # SPLIT — keeps Tier-2 only (assignment, balance, capacity)
│   └── tier3_cpsat.py      # NEW — OR-Tools CP-SAT model for sequencing
├── solve/
│   ├── solver.py           # SPLIT — Tier-2 solver wrapper unchanged
│   ├── solver_cpsat.py     # NEW — OR-Tools CP-SAT wrapper
│   └── orchestrator.py     # NEW — runs Tier-2 → Tier-3 → (optional retry loop)
├── output/
│   └── gantt.py            # UPGRADE — shift-level Gantt from CP-SAT intervals

The MILP model loses ~5 constraints (the linearised changeover + co_team blocks); CP-SAT gains them in tighter form. Net code size: roughly neutral, but solve time drops because the LP relaxation of the MILP is now much tighter without big-M on changeover.

2.4 Implementation steps

  1. Strip the changeover linearisation (changeover_link, co_team) from model/build.py. Leave co_pack as a Tier-3 output only.
  2. Write model/tier3_cpsat.py:
    • Interval/IntervalVar per (order, machine, week) with size = qty/throughput minutes.
    • add_no_overlap per machine-week (single resource).
    • transition_time matrix from changeover_h[m, f1, f2].
    • One global no_overlap resource for the changeover team across all machines.
    • Forbidden assignments for EVATON (2-batch / 3-week gap).
  3. solve/orchestrator.py:
    def solve_quarter(params, cfg):
        milp_model = build_milp(params)
        milp_result = solve_milp(milp_model, cfg)
        sequence_plan, infeasible_weeks = solve_cpsat(milp_result, params, cfg)
        while infeasible_weeks and iters < 3:
            milp_model = add_cuts(milp_model, infeasible_weeks)
            milp_result = solve_milp(milp_model, cfg)
            sequence_plan, infeasible_weeks = solve_cpsat(milp_result, params, cfg)
        return merge(milp_result, sequence_plan)
  4. Update output/gantt.py to render minute-granularity intervals from CP-SAT.
  5. Update tests in tests/test_q1_smoke.py to assert minute-level no-overlap.

2.5 Expected gains

  • Solve time: 10 min → 2–3 min on the same Q1 instance.
  • Changeover plan: weekly granularity → shift-level.
  • The changeover model becomes tight (CP-SAT propagates transition_time exactly), so the objective can rely on real changeover-hour totals.
  • Unlocks proper req #16 ("re-plan in seconds on disruption") because CP-SAT can re-solve a single week in <5s.

3. Constraint catalog — every rule as data

3.1 Why move beyond defaults.yaml

v1 splits the world into:

  • Parameters (in defaults.yaml) — numbers
  • Constraints (in model/constraints.py) — Python code

Phase 2 collapses these: a constraint is a structured row whose parameters field holds the numbers, whose formal_expr field holds the rule, whose solver_layer field tells the orchestrator where to instantiate it, and whose version field makes changes auditable.

3.2 Schema — catalog/constraints/*.yaml

One file per constraint. Schema:

# catalog/constraints/C-037-piramal-band.yaml
id: C-037
req_ref: req #37
category: customer_band              # customer_band | sequencing | capacity | …
name: Piramal monthly volume band
description: |
  Piramal must receive between 1.8M and 2.0M ampoules per calendar month.
  Data shows 2.0–2.8M/month for 2025; open question — see MODEL_SCOPING §10.
severity: soft                       # hard | soft (soft adds penalised slack)
solver_layer: MILP_master            # MILP_master | CP_SAT_seq | both
enabled: true

# Symbolic form — what gets compiled to Pyomo / CP-SAT.
formal_expr:
  type: two_sided_bound
  index_over: [month]
  lhs: "sum(o in O_piramal, w in month(t)) vol_pack[o, m, w] for all m"
  bound_min: parameters.monthly_min
  bound_max: parameters.monthly_max

parameters:
  monthly_min: 1_800_000
  monthly_max: 2_000_000

# Soft-mode slack handling (omitted when severity = hard).
soft_handling:
  under_var: piramal_under
  over_var:  piramal_over
  penalty_weight: objective_weights.late   # reference to the weights block

# Verifier hooks
units:
  bound_min: ampoules_per_month
  bound_max: ampoules_per_month
business_rules:
  - "any change to monthly_max above 2.5M requires Sales-VP approval"
  - "monthly_min cannot go below 1.5M while supply contract X-2024 is active"

owner: Sales/Account Mgr
version: 2026-05-11.v1
verifier_state: passed
audit_log_ref: "catalog/audit/C-037-history.jsonl"

formal_expr.type enumerates ~12 patterns covering all 15+3 v1 constraints (see §3.4). A constraint compiler walks the catalog and emits Pyomo or CP-SAT code:

# model/compile.py
def compile_catalog(catalog: list[CatalogRow], target: Literal["MILP", "CP-SAT"]) -> ConstraintBlock:
    blocks = []
    for row in catalog:
        if not row.enabled:
            continue
        if row.solver_layer != target and row.solver_layer != "both":
            continue
        compiler = COMPILERS[row.formal_expr.type]  # plugin per pattern
        blocks.append(compiler(row, target))
    return blocks

3.3 The 15 + 3 v1 constraints as catalog rows

Catalog ID Req Pattern type Layer Severity
C-001 one-format-per-cycle #8 sum_le MILP_master hard
C-002 demand-fulfilment #2,#10 balance MILP_master hard
C-003 order-machine-eligibility implicit sparse_set MILP_master hard
C-004 glass-volume-thresholds #31,#32 range_eligibility MILP_master hard
C-005 org-no-split #39 single_placement MILP_master hard
C-006 piramal-band #37 two_sided_bound MILP_master soft
C-007 farcon-xor-dividella #35 mutex MILP_master hard
C-008 changeover-team-no-overlap #36 resource_no_overlap CP_SAT_seq hard
C-009 prod-pack-lag-4d #46 precedence_lag MILP_master hard
C-010 prod-label-lag-3d #46 precedence_lag MILP_master hard
C-011 one-api-per-week #42 sum_le MILP_master hard (toggleable)
C-012 campaign-coverage-by-sl #45 aggregated_demand MILP_master hard
C-013 shelf-life-storage-cap #48 time_window CP_SAT_seq hard
C-014 evaton-2-batch-3-week-gap #49 forbidden_assignments CP_SAT_seq hard
C-015 capacity-hours #5,#19 capacity_eq MILP_master hard
C-040 tie-fairness #40 deviation_penalty MILP_master soft
C-041 highest-score-first #41 lex_min MILP_master soft
C-038 minor-format-changes-allowed #38 relaxation_marker both soft

3.4 Pattern compiler — keeping the grammar small

The catalog stays expressive but the compiler surface is bounded. A new constraint that fits an existing pattern is a YAML edit; a constraint that needs a new pattern is a code change to add one compiler plugin (one function in model/compilers/).

The 12 patterns cover everything in the current 50-requirement spec; we expect ≤5 new patterns over the first year as edge cases surface.

3.5 Versioning, diff, and audit

Every catalog write is a new version. The full history of a constraint lives under catalog/audit/<id>-history.jsonl:

{"ts": "2026-05-11T17:42:00Z", "id": "C-037", "from": "v1", "to": "v2",
 "change": {"parameters.monthly_max": [2_000_000, 2_500_000]},
 "actor": "user:cgapho...", "rationale": "Sales contract update Q3",
 "verifier_runs": ["schema:pass", "unit:pass", "feasibility:pass", "business:pass"],
 "objective_delta": "+0.4% rated OTIF", "approved_by": "user:cgapho..."}

The Audit MCP service serves this; the Verifier reads it for business-rule checks.

3.6 Visibility to the LLM

The LLM only ever sees the catalog, the last plan, and the metadata about the run (status, KPIs, IIS). It never sees the Pyomo model object itself. The catalog is YAML, so it's natively human/LLM readable.

Specifically:

  • Catalog MCP exposes: list_constraints, get_constraint(id), propose_patch(id, change), commit_patch(patch_id), rollback(id, version).
  • Solver MCP exposes: solve(catalog_version, horizon), last_run(), iis(infeasible_run_id).
  • Plan MCP exposes: get_plan(run_id), compare_plans(run_a, run_b).

4. Agents — seven roles, three stages

# Agent Stage Reads Writes Trigger
0 Supervisor orchestration user intent sub-agent invocation graph every user turn
1 Constraint-Elicitation PRE-solve catalog, user NL request catalog patch (proposed) user says "change/add a rule"
2 Schedule-Generation PRE-solve catalog, data snapshot, knobs solver call (Tier-1 → 4) user says "run scheduler" or catalog change committed
3 Infeasibility POST-solve IIS / minimal infeasible subsystem NL narration of which constraints clash solver returns infeasible
4 What-If POST-solve two plans (before/after) NL narration of the delta + KPI diff catalog patch ready to compare
5 Explanation POST-solve committed plan + persona context persona-tuned text (Sales / Production / Compliance) new plan committed
6 Disruption-Response LIVE Telemetry MCP events + current plan LNS repair patch + narration Photocells freeze ≥ τ minutes

4.1 Where each agent sits in the loop

USER ───►  Supervisor ──┐
                        │
                  ┌─────┴───────┐
                  │             │
           "edit rule"     "run / explain"
                  │             │
                  ▼             ▼
      Constraint-Elicit   Schedule-Generation
                  │             │
                  ▼             ▼
              VERIFIER     SOLVER CHAIN  ────►  if infeasible ──► Infeasibility
                  │             │
                  ▼             ▼
            catalog v+1     plan_v+1 ────►  What-If (vs plan_v) ──► Explanation
                  │             │
                  └──────┬──────┘
                         │
                         ▼
                    APPROVAL QUEUE
                         │
                         ▼
                    SAP push  +  AUDIT

Live (independent of above):
  Telemetry ──► Disruption-Response ──► Tier-4 LNS ──► VERIFIER ──► SAP push

4.2 What each agent is allowed to do

  • Constraint-Elicitation writes catalog patches only — never solver calls, never SAP. Output must be a structured patch object the Verifier can check.
  • Schedule-Generation calls the Solver MCP and returns the result reference. It does not interpret numbers — that's downstream.
  • Infeasibility reads IIS and narrates. It can propose a relaxation (e.g. "if you let C-037 monthly_max rise by 0.5M, this becomes feasible") but cannot apply it.
  • What-If runs two catalog versions through the Solver MCP and reports the KPI diff plus a 3-bullet rationale.
  • Explanation is a renderer — it cannot mutate state.
  • Disruption-Response is the only agent allowed to act fast: it can call Tier-4 LNS and push to SAP after the Verifier passes, all within ~1 minute.
  • Supervisor routes; it does not solve or write.

4.3 What the Verifier does (the trust boundary)

Between every agent output and the system of record:

Agent output (catalog patch | plan | SAP write request)
      │
      ▼
Verifier
  ├── schema check     (pydantic on the patch / plan dataclass)
  ├── unit check       (cross-check parameter units against catalog `units` block)
  ├── feasibility check (run a *warm-cached* solver on the patched catalog)
  ├── business-rule check (cross-check `business_rules` block against actor/context)
  └── audit log         (append to immutable JSONL)
      │
      ▼
Commit ←── all pass ───→  reject (NL reason returned to the agent)

The Verifier is deterministic — no LLM in it. That is what allows the LLM agents to be opinionated without being load-bearing on correctness.


5. Replan flow — quantifiable constraint change, end to end

5.1 The scenario

User chats: "Raise Piramal monthly band to 2.5M, starting in Q1."

5.2 Step-by-step

1. SUPERVISOR
   parses intent → "modify existing constraint" → route to Constraint-Elicitation

2. CONSTRAINT-ELICITATION AGENT
   reads catalog/constraints/C-037-piramal-band.yaml (v1)
   drafts patch:
     PATCH C-037 v1 → v2
       parameters.monthly_max: 2_000_000 → 2_500_000
       version: 2026-05-11.v1 → 2026-05-11.v2
   passes patch to Verifier

3. VERIFIER (deterministic, ~1s)
   ├── schema:        OK (correct type, two_sided_bound pattern still valid)
   ├── unit:          OK (still ampoules/month)
   ├── feasibility:   runs cached-warm solve on draft catalog → SAT (the new max
   │                   is more permissive than v1 — was always going to be SAT
   │                   given v1 was soft anyway)
   ├── business-rule: C-037.business_rules says "above 2.5M requires Sales-VP
   │                   approval" — 2.5M is the boundary; this rule fires a
   │                   GATE that requires Sales-VP sign-off. Returns
   │                   "needs_approval: sales_vp"
   └── audit: draft logged

   If gate fires → BLOCK with NL reason returned via Supervisor to user:
     "C-037 raise to 2.5M needs Sales-VP approval per the business rule
      attached to this constraint. Forward to VP?"

   If gate clears (Sales-VP approves in app) → continue.

4. CATALOG COMMIT
   New row written: C-037 v2
   audit/C-037-history.jsonl appended
   Catalog MCP returns the new catalog version id (e.g. catalog v37 → v38)

5. SCHEDULE-GENERATION AGENT
   triggers SOLVER CHAIN against catalog v38:
     Tier-1 LP   ── 5s   → annual feasibility envelope (unchanged)
     Tier-2 MILP ── 90s  → new (x_pack, y_pack, qty_prod) — Piramal can absorb more
     Tier-3 CP-SAT ── 30s → new sequence + changeover plan
     DES Simulator ── 20s → robustness OK
   solver writes plan_v38 to Plan MCP

6. WHAT-IF AGENT
   reads plan_v37 (before) and plan_v38 (after); produces:

   "Catalog C-037 v1 → v2 (Piramal band 2.0M → 2.5M monthly):

    • Piramal monthly band slack: was [0, 1.6M, 2.2M] over → now [0, 0, 0].
    • Rated OTIF: 97.9% → 99.1% (+1.2 pts).
    • Total changeover hours: 14h → 18h (+4h).
    • Piramal unfilled: 853k → 0.
    • Marchesini GL utilisation: 53.7% → 58.4%.
    • One extra changeover on Dividella W7."

7. EXPLANATION AGENT
   renders three persona-tuned views from plan_v38 + the What-If delta:
     ├── Sales view:       "Piramal Q1 will ship at full demand. Three Greek
     │                      and UK orders move from W3 to W4 to absorb the
     │                      capacity shift."
     ├── Production view:  Gantt with the +1 changeover on Dividella W7,
     │                      Marchesini W6/W8 reshuffled, KPI utilisation chart.
     └── Compliance view:  audit summary, Sales-VP approval timestamp,
                           catalog diff link, plan id, run id.

8. APPROVAL QUEUE → SAP PUSH
   user reviews the three views
   user clicks "approve and commit"
     ├── Audit MCP append:  plan_v38 commit + actor + rationale
     ├── SAP Bridge MCP:    write Process Orders for v38 (only delta from v37)
     └── Telemetry MCP:     subscribes the new plan to live monitoring

9. (If user rejects)
   ├── Catalog rollback: C-037 v2 marked obsolete, plan_v38 marked rejected
   ├── Audit log records rejection rationale
   └── Telemetry continues monitoring plan_v37

5.3 What this gives the user that v1 doesn't

v1 (Phase 1) v2 (Phase 2)
Edit configs/defaults.yaml, re-run CLI, read JSON Chat "raise band to 2.5M"
You need to know the parameter name Constraint-Elicitation finds it by NL
You don't know if the change broke another rule Verifier checks feasibility + business rules
You compare two JSONs by eye What-If narrates the delta in 5 bullets
You decide what to tell Sales / Production / Compliance Explanation renders all three
You write to SAP yourself, hopefully Audit + SAP push are gated behind a single approval

5.4 Latency budget for the loop

Step Time
NL → patch (Constraint-Elicitation) 2–4 s
Verifier (no solver) <1 s
Verifier feasibility check (cached warm solve) 10–30 s
Catalog commit <1 s
Tier-1 + Tier-2 + Tier-3 + DES 2–4 min
What-If diff narration 3–5 s
Explanation render (3 views) 5–10 s
Total user-visible round trip 3–5 min

Live disruption (Disruption-Response) targets <60 s end-to-end via LNS.


6. Build order — three sub-phases

Phase 2a — CP-SAT split (2 weeks)

  • Carve out model/tier3_cpsat.py, solve/solver_cpsat.py, solve/orchestrator.py.
  • Move C-008 (changeover team), C-013 (shelf-life storage), C-014 (EVATON gap) into CP-SAT.
  • Keep defaults.yaml as the parameter source — catalog comes in 2b.
  • Verify Q1 still hits ≥95% OTIF in <3 min.
  • Verify the smoke test post-hoc checks pass at minute-granularity (CP-SAT outputs minute starts).

Phase 2b — Constraint catalog (3 weeks)

  • Define the 12 pattern types + compiler plugins in model/compilers/.
  • Migrate the 15+3 constraints from Python into catalog/constraints/*.yaml.
  • model/build.py becomes model/compile.py — assembles MILP from catalog.
  • solve/orchestrator.py accepts a catalog version id and pins the run to it.
  • Add Audit MCP (file-backed JSONL) + Catalog MCP (filesystem-backed YAML watcher).
  • Deprecate configs/defaults.yaml (its contents migrate into the catalog and a slim knobs.yaml).

Phase 2c — Agent loop (4 weeks)

  • LangGraph supervisor + 7 sub-agents.
  • Verifier (deterministic checks + solver-cached feasibility probe).
  • MCP servers for Catalog, Solver, Plan, Audit, SAP Bridge stub.
  • Approval queue UI (simple web page is fine for v2).
  • End-to-end "change Piramal band" smoke test passes the §5.2 flow in <5 min.

After 2c, Phase 3 (Tier-4 LNS, Photocells/ProdAction telemetry, real SAP bridge) becomes incremental.


7. Risks and mitigations

Risk Likelihood Mitigation
CP-SAT model is slower than expected on tight no-overlap Low Bench on Q1 first; fall back to linearised MILP (Phase-1 default) if needed
Catalog compiler grammar can't express a rule Med Keep compiler plugin model open; new pattern = one function
LLM proposes invalid patches High Verifier rejects with NL reason; agent retries with the reason
User changes a constraint that's still under another agent's review Med Catalog uses optimistic concurrency on version; second commit re-bases or fails
Feasibility check in Verifier is slow Med Use cached warm-started solve on a frozen sub-model — 5–30 s, not 10 min
Sales-VP approval gate not modelled in v2 Med Business-rule check returns a gate signal; UI shows the approval queue

8. Out of scope for Phase 2

  • Real-time Photocells/ProdAction telemetry feeds (Phase 3).
  • LNS repair on disruption (Phase 3 — Disruption-Response agent is stubbed in 2c).
  • True SAP write-back (Phase 3 — SAP Bridge is a stub in 2c that writes to a file).
  • Multi-tenant catalog / RBAC (Phase 4).
  • Plastic ampoules / bottles / lyophilised (Phase 4 — req #34 scope).
  • Re-rating customers automatically (Phase 4 — owned by Sales).

9. Glossary

Term Meaning
Catalog The versioned YAML store of all constraints + their parameters + their solver layer. Source of truth for "what the rules are."
Compiler plugin Function that turns one formal_expr.type into Pyomo (or CP-SAT) constraints.
CP-SAT Google OR-Tools constraint-programming solver; owns the sequencing layer in Phase 2.
IIS Irreducible Infeasible Subsystem — minimal set of constraints whose conflict makes a solve infeasible.
LangGraph LangChain's stateful agent-orchestration framework.
LNS Large Neighborhood Search — repairs a plan by destroying and re-solving a small window.
MCP Model Context Protocol — Anthropic's tool/service protocol; every backend (Catalog, Solver, Plan, Audit, SAP) is an MCP server.
Patch Proposed change to a catalog row — JSON-style diff applied via propose_patch.
Verifier Deterministic check (schema/unit/feasibility/business) that gates every agent output. Not an LLM.
Warm cache Pre-built solver state reused across feasibility checks so the Verifier's solve takes seconds, not minutes.